Mining

Project Details

  • SERVICE TYPE:Control Automation

Electrical Replacement of Main/North Wing Conveyors and Truck Dump Stations, 8000’ and 12,000’ respectively, were required to be upgraded from 1400tph to 2400tph. Project included upgrades and replacement of existing MCC buildings with new buildings containing VFD drives, all control devices, and a complete upgrade of the automation platform. All upgrades were coordinated to minimize downtime.


Share this post

Management

BODEC, Inc. and Bruno Engineering, P.C. have built a team of seasoned professionals with the technical knowledge and experience to complete even the most complex designs and installations. Our management team is available to our customers and acts as a resource for our crews on every project.
About Us