PV Collector Substation in Idaho

230 kV/34.5 kV- 138/184/230 MVA

Construction Dates:
July 2024 – October 2024

Total Project Value:
$9,100,000.00

Scope of Work:

  • Conceptual design for customer buy-in
  • Civil, structural, electrical & communications engineering
  • Control building design & construction
  • Equipment procurement (owner-provided GSU & Main Breaker)
  • Full project management
  • Stakeholder coordination
  • Fence, civil, structural & electrical construction
  • HSE compliance
  • Testing & commissioning
  • QA/QC oversight
  • Documentation & handover
  • Third-party NETA testing