Scofield Dam Project

Scofield Dam Project

BODEC was part of the Scofield Dam Modification project. With various partnerships and funding for this project, we were proud to be one of many teams working to restore the former Blue Ribbon trout population of Lower Fish Creek.

Construction Dates:
Jan 2023- April 2023

Scope of Work:

  • Install 8” Pressure Gate S-45 with articulated gate stem & brackets.
  • Drilled 8” hole through existing chamber wall.
  • Install 8” steel pipe, fittings, & anchors