Switch House Electrical Infrastructure

Design and construction of a new 34.5 kV distribution system, including feeder upgrades and relay integration to modernize facility power infrastructure.

Switch House 34.5 kV distribution gear, overhead feeders, fiber optic trip system, and ring bus configuration.

Construction Dates

September 2021 – November 2022

Total Project Value

$7,500,000

Scope of work

  • Designed and installed new 34.5 kV distribution gear in an E-House
  • Constructed four overhead 34.5 kV feeders from utility substation to distribution building
  • Designed feeder system for seamless cutover from legacy gear
  • Designed and built fiber optic trip system for main feeders
  • Created a 34.5 kV ring bus for flexible, reliable power transfer
  • Programmed and integrated relays with utility for full system coordination