Switch House 34.5 kV distribution gear, overhead feeders, fiber optic trip system, and ring bus configuration.
Construction Dates:
September 2021 – November 2022
Total Project Value:
$7,500,000
Scope of Work:
- Designed and installed new 34.5 kV distribution gear in an E-House
- Constructed four overhead 34.5 kV feeders from utility substation to distribution building
- Designed feeder system for seamless cutover from legacy gear
- Designed and built fiber optic trip system for main feeders
- Created a 34.5 kV ring bus for flexible, reliable power transfer
- Programmed and integrated relays with utility for full system coordination