345kV PV Collector Substation with T-Line EPC

345kV PV Collector Substation with T-Line

PV Substation:

200 MVA, Two 345/34.5kV transformers, Three 345kV SF6 breakers, Seven MV collection feeder breakers arranged on two buses.

T-Line:

2.5 miles of 345kV T-line, bundled 795 Drake ACSR.

Construction Dates:
July 2022 – December 2023

Total Project Value:
$9,700,000.00

Scope of Work:

  • Multi-Discipline Design
  • Electrical- Power & SCADA
  • Civil
  • Structural
  • Arc-Flash, Short-Circuit, Relay Coordination Studies
  • Relay/SCADA setpoint & programming
  • Equipment specifications
  • On-site Construction Activities
  • Materials management and procurement
  • Construction of control building
  • System commissioning & start-up 3rd-party testing