Electrical dam and dike modifications
Construction Dates:
October 2019 – April 2021
Total Project Value:
$185,000
Scope of Work:
- De-energization and demolition of existing electrical system.
- Installation of new three-phase electrical service.
- Installation of new electrical system.
- Demolition and salvage of existing SCADA system.
- Installation of upgraded SCADA system for operating and monitoring canal and river gates.