Repurposed Substation &
Powerline EPC

Substation & Powerline EPC Design Build

Substation– 10/12.5 MVA, 46 kV – 12.47 kV, Resistance Grounded four outputs with 15kV feeders.

Powerline– 3.1 miles of 46 kV High-line, #4/0 ACSR “Penguin,” Raptor-Proof Design.

Construction Dates:
August 2020 – December 2020

Total Project Value:
$2,735,000

Scope of Work:

  • Multi-Discipline Design
  • Electrical- Power & SCADA
  • Civil
  • Structural
  • Arc-Flash, Short-Circuit, Relay Coordination Studies.
  • Relay/ SCADA setpoint and programming.
  • Equipment specifications.
  • On-site Construction Activities.
  • Materials management and procurement.
  • Offloading/construction of control buildings.
  • System commissioning & start-up.
  • Project/Safety Management- QA/QC.
  • 3rd-party NETA testing.
  • 15 kV mine feeder output cables hung into mine through 800′ raise bore shaft.
  • Re-use and integration of substation equipment from a former mine site.