Water Management 1200A 480 V System Implementation.
Construction Dates:
April 2021 – December 2021
Total Project Value:
$700,000
Scope of Work
- Installation of customer provided equipment.
- Installation of DCS equipment.
- Furnish & Install BOP raceway & mechanical equipment.
- Furnish & Install fiber communication network.
- Design, Furnish, and Install BOP heat trace.
- Test & start-up